Our latest video showcases the exciting progress over the last few months, including:
Stage 3
- Statement of Compliance received.
- Titles expected late April 2021.
Stage 4
- Kerb and channel completed.
- Road pavement and concreting underway.
- Titles expected June 2021.
Stage 5
- Earthworks complete.
- Sewer, drainage, and road boxing underway.
- Titles expected October 2021.
Stage 6
- Earthworks complete.
- Sewer underway.
- Titles expected December 2021.
Stage 7
- Earthworks complete.
- Sewer underway.
- Titles expected December 2021.
Stage 9
- Earthworks complete.
- Sewer underway.
- Titles expected January 2022.