Orana has been busy with construction activity and we’re excited to share with you the amazing progress that our construction team has made.
Stage 5
– Final concrete works and topsoil works underway
– Titles expected November 2021
Stage 6
– Drainage, water, and gas infrastructure nearing completion
– Electrical, NBN, and road pavement base layers underway
– Titles expected April 2022
Stage 7
– Drainage, water, and gas infrastructure underway
– Titles expected April 2022
Stage 9
– Drainage works underway with water and gas infrastructure nearing commencement
– Titles expected June 2022
Stage 13
– Road boxing, subgrade preparation and sewer works underway
– Titles expected July 2022
Stage 14
– Road boxing and subgrade preparation works underway
– Titles expected September 2022
Stage 11
– Earthworks underway
– Titles expected Q4 2022
Stage 12
– Earthworks underway
– Titles expected Q4 2022