The year has already started with a bang and what better way to kick off than with our January Construction Update! The Orana team has been busy over the past few weeks to achieve some exciting construction milestones. excited to share some fantastic progress updates at Orana!
CIVIL CONSTRUCTION
Stage 20
Stage 20 has been progressing well, with sewer, sub-grade pavement & drainage pipe installations now complete as we wrap up the summer holiday period. This has allowed for the completion of drainage pits, ag drains and the initial pavement rock layers by January 2025. Looking ahead, we’re excited to begin water, gas reticulation, and kerb installation works in February 2025. Title registration is anticipated in May 2025.
Stage 21
The final section of the 1.3m diameter Melbourne Water drain in Stage 21 has been completed, and with work resuming after the summer break, the sub-grade works are on track to finish in early February 2025. Following that, we’ll move forward with City of Casey Council drainage, ag drains, and rock pavement layers. Title registration for this stage is forecasted for Q3 2025.
Riverland Road
Riverland Road has seen significant progress throughout December 2024 and January 2025. Bulk earthworks, sewer, drainage, water & gas installation, sub-grade placement, initial pavement rock layers, and kerb installation have all been completed. This sets us up for a busy February 2025 for the Orana Town Centre, where we’ll focus on finalising footpaths, asphalt, and topsoil works, as well as commencing initial compliance items. Title registration for this area remains projected for Q1 2025.
LANDSCAPING CONSTRUCTION
Stage 13 Townhomes (including Orana Blvd frontage): Our landscaping team has made great progress on the nature strips in this area, with 80% of the works now completed. We’re also gearing up to finalise the garden beds within the townhome site soon.
Stage 13 (Swale and Boysenberry Close): Rectification works are underway, with mulch and infill planting progressing well. Our team is expected to complete these tasks by the end of next week.
Stages 8, 10, 11 & 12: Nature strips that were previously obstructed by builder works or bins are now being completed. Our team is on track to finalise these areas by mid-February.
Stay connected and fly above our community to see the progress by clicking here! You can also track the construction and title registration status of your lot via here, where all the details you need to oversee your build are readily available.