Click through for full details on stage by stage updates or our latest aerial update.
We are pleased to announce that the civil works for the Pattersons Road Intersection were completed on February 26, 2026. Thanks to the hard work of our civil teams, this critical piece of infrastructure was finalized one month ahead of schedule, ensuring smoother access for the growing community.
The Stage 22 Park: A New Destination
The heart of Stage 22 is coming to life! Following the completion of bulk earthworks in January, we have seen significant progress on the local park:
Streetscape Updates
Stage 22
Civil construction is now 100% complete. We are currently working with the relevant authorities to achieve statement of compliance, which is on track for mid-March.
Anticipated Titles: Late March 2026
Stage 23
Progress remains steady with earthworks, sewer, and subgrade works now finished. Our focus has shifted to drainage installation, which will allow us to start water mains within the next two weeks
Anticipated Titles: Late Q2 2026
Stage 24A
As the final piece of the puzzle within “Permit Area C,” Stage 24A officially commenced in February. Because sewer works were completed during the previous stage, we have been able to fast-track earthworks, drainage, and water mains
Anticipated Completion: Mid-2026