Earthworks, subgrade, sewer and drainage works are now complete in Stage 27, and water infrastructure is well underway. Construction of the concrete laneways and footpaths begins next week, with kerb and electrical works following close behind.
A major milestone has also been reached with the successful commencement of construction of the large Melbourne Water wetland south of Pattersons Road.
The wetland will form an important piece of Orana’s broader drainage and environmental infrastructure, while also contributing to the growing network of open space and natural landscape features throughout the community.
Construction is now underway, marking another significant step forward in the delivery of this important piece of infrastructure.
The Stage 21 streetscapes are continuing to take shape. Soil preparation is nearly complete, around half of the street trees are now in the ground, and planting has commenced. Practical Completion is expected by the end of October 2026.
In Stage 23, all landscape works are now complete, with Practical Completion achieved in August 2026. Around Orana Village, all landscape works have now been constructed, just in time for the opening of Orana Village Shopping Centre.A small number of remaining naturestrips south of Pattersons Road will be installed during the maintenance period, once builders have completed their works.
With construction progressing across multiple areas of the community, Orana continues to evolve each month, with new infrastructure, streetscapes and open spaces bringing the masterplanned community closer to completion.
We look forward to sharing more progress as these new streets and landscapes continue to grow and settle in.