Delivery

Stage Updates

Stages In Progress:

Stage 18

The Lomandra Release

Civil
50
Registration

Construction Commenced

January 23

Estimated Title Registration

Q3 2024

Site Establishment

Site Establishment


This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

100%

Bulk Earthworks

Bulk Earthworks


The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

100%

Sewer Works

Sewer Works


The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

100%

Drainage Works

Drainage Works


The provision of underground drainage and channel/retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

25%

Water & Gas Reticulation

Water & Gas Reticulation


The provision of water and gas pipelines with a connection to each lot.

0%

Subgrade Placement Works

Subgrade Placement Works


The engineered material that provides a firm base underneath a constructed road pavement.

100%

Electrical & NBN

Electrical & NBN


The supply of electricity and NBN (high speed internet) to each lot.

0%

Footpaths /Asphalt / Linemarking

Footpaths /Asphalt / Linemarking


The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement.

0%

Practical Completion

Practical Completion


The completion of the construction works.

0%

Registration

Statement of Compliance

Statement of Compliance


The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

0%

Lodge Plan of Subdivision

Lodge Plan of Subdivision


The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

0%

Titles

Titles


The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor's reports.

0%

Settlement

Settlement


The legal transfer of the residential lot from the developer to the prospective home owner.

0%

Show Details

Stages Completed:

Stage 1

Display Village

Stage 14

The Grevillea & Pandorea Release

Stage 24

The Lily Release

January 24

Stage 16

The Arbor Release

Show More

Disclaimer: Estimated title dates are provided as an approximate guide only and are subject to change. The title date estimates provided are based on current information regarding the design, construction, and relevant authority approvals timeframes for the individual stage. Balcon uses this information to provide an estimate of the month (or month/quarter ranges) in which titles will be achieved however this is subject to change and may be influenced by factors which are outside Balcon’s control such as weather, contractor delays and authority inspections. Balcon is not bound by any of the information or date estimates set out on this webpage. Balcon does not give any warranty in relation to any information contained in this webpage and does not accept any liability for loss or damage arising as a result of any reliance on the information on this webpage. The sale of a lot at Orana by Balcon is subject to the conditions of a contract of sale entered into between the purchaser and the vendor of the lot. The contract of sale is the entire agreement between the vendor and purchaser. All purchasers should rely solely on the terms of the contract of sale and obtain their own independent legal advice in relation to the terms of the contract of sale.