Delivery

Stage Updates

Stages In Progress:

Stage 9

The Gum Release

Civil
90
Registration

Estimated Title Registration

August 2022

Civil Phase

90%

Site Establishment

Site Establishment


This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

100%

Bulk Earthworks

Bulk Earthworks


The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

100%

Drainage Works

Drainage Works


The provision of underground drainage and channel/retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

100%

Sewer Works

Sewer Works


The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

100%

Water & Gas Reticulation

Water & Gas Reticulation


The provision of water and gas pipelines with a connection to each lot.

100%

Subgrade Placement Works

Subgrade Placement Works


The engineered material that provides a firm base underneath a constructed road pavement.

100%

Electrical & NBN

Electrical & NBN


The supply of electricity and NBN (high speed internet) to each lot.

100%

Footpaths / Asphalt / Linemarking

Footpaths / Asphalt / Linemarking


The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement.

100%

Practical Completion

Practical Completion


The completion of the construction works.

0%

Registration Phase

Statement of Compliance

Statement of Compliance


The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

0%

Lodge Plan of Subdivision

Lodge Plan of Subdivision


The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

0%

Titles

Titles


The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor's reports.

0%

Show Details
Stage 13

The Ash Release

Civil
80
Registration

Estimated Title Registration

September 2022

Civil Phase

80%

Site Establishment

Site Establishment


This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

100%

Bulk Earthworks

Bulk Earthworks


The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

100%

Drainage Works

Drainage Works


The provision of underground drainage and channel/retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

100%

Sewer Works

Sewer Works


The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

100%

Water & Gas Reticulation

Water & Gas Reticulation


The provision of water and gas pipelines with a connection to each lot.

100%

Subgrade Placement Works

Subgrade Placement Works


The engineered material that provides a firm base underneath a constructed road pavement.

100%

Electrical & NBN

Electrical & NBN


The supply of electricity and NBN (high speed internet) to each lot.

100%

Footpaths / Asphalt / Linemarking

Footpaths / Asphalt / Linemarking


The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement.

0%

Practical Completion

Practical Completion


The completion of the construction works.

0%

Registration Phase

Statement of Compliance

Statement of Compliance


The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

0%

Lodge Plan of Subdivision

Lodge Plan of Subdivision


The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

0%

Titles

Titles


The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor's reports.

0%

Show Details
Stage 14

The Grevillea & Pandorea Release

Civil
70
Registration

Estimated Title Registration

November 2022

Civil Phase

70%

Site Establishment

Site Establishment


This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

100%

Bulk Earthworks

Bulk Earthworks


The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

100%

Drainage Works

Drainage Works


The provision of underground drainage and channel/retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

100%

Sewer Works

Sewer Works


The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

100%

Water & Gas Reticulation

Water & Gas Reticulation


The provision of water and gas pipelines with a connection to each lot.

100%

Subgrade Placement Works

Subgrade Placement Works


The engineered material that provides a firm base underneath a constructed road pavement.

100%

Electrical & NBN

Electrical & NBN


The supply of electricity and NBN (high speed internet) to each lot.

0%

Footpaths / Asphalt / Linemarking

Footpaths / Asphalt / Linemarking


The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement.

0%

Practical Completion

Practical Completion


The completion of the construction works.

0%

Registration Phase

Statement of Compliance

Statement of Compliance


The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

0%

Lodge Plan of Subdivision

Lodge Plan of Subdivision


The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

0%

Titles

Titles


The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor's reports.

0%

Show Details
Stage 11

The Wattle Release

Civil
40
Registration

Estimated Title Registration

Q1 2023

Civil Phase

40%

Site Establishment

Site Establishment


This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

100%

Bulk Earthworks

Bulk Earthworks


The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

100%

Drainage Works

Drainage Works


The provision of underground drainage and channel/retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

100%

Sewer Works

Sewer Works


The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

100%

Water & Gas Reticulation

Water & Gas Reticulation


The provision of water and gas pipelines with a connection to each lot.

0%

Subgrade Placement Works

Subgrade Placement Works


The engineered material that provides a firm base underneath a constructed road pavement.

0%

Electrical & NBN

Electrical & NBN


The supply of electricity and NBN (high speed internet) to each lot.

0%

Footpaths / Asphalt / Linemarking

Footpaths / Asphalt / Linemarking


The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement.

0%

Practical Completion

Practical Completion


The completion of the construction works.

0%

Registration Phase

Statement of Compliance

Statement of Compliance


The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

0%

Lodge Plan of Subdivision

Lodge Plan of Subdivision


The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

0%

Titles

Titles


The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor's reports.

0%

Show Details
Stage 12

The Linden Release

Civil
30
Registration

Estimated Title Registration

Q1 2023

Civil Phase

30%

Site Establishment

Site Establishment


This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

100%

Bulk Earthworks

Bulk Earthworks


The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

100%

Drainage Works

Drainage Works


The provision of underground drainage and channel/retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

25%

Sewer Works

Sewer Works


The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

25%

Water & Gas Reticulation

Water & Gas Reticulation


The provision of water and gas pipelines with a connection to each lot.

0%

Subgrade Placement Works

Subgrade Placement Works


The engineered material that provides a firm base underneath a constructed road pavement.

0%

Electrical & NBN

Electrical & NBN


The supply of electricity and NBN (high speed internet) to each lot.

0%

Footpaths / Asphalt / Linemarking

Footpaths / Asphalt / Linemarking


The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement.

0%

Practical Completion

Practical Completion


The completion of the construction works.

0%

Registration Phase

Statement of Compliance

Statement of Compliance


The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

0%

Lodge Plan of Subdivision

Lodge Plan of Subdivision


The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

0%

Titles

Titles


The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor's reports.

0%

Show Details
Stage 10

The Daniella Release

Civil
20
Registration

Estimated Title Registration

Q1 2023

Civil Phase

20%

Site Establishment

Site Establishment


This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

100%

Bulk Earthworks

Bulk Earthworks


The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

100%

Drainage Works

Drainage Works


The provision of underground drainage and channel/retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

0%

Sewer Works

Sewer Works


The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

0%

Water & Gas Reticulation

Water & Gas Reticulation


The provision of water and gas pipelines with a connection to each lot.

0%

Subgrade Placement Works

Subgrade Placement Works


The engineered material that provides a firm base underneath a constructed road pavement.

0%

Electrical & NBN

Electrical & NBN


The supply of electricity and NBN (high speed internet) to each lot.

0%

Footpaths / Asphalt / Linemarking

Footpaths / Asphalt / Linemarking


The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement.

0%

Practical Completion

Practical Completion


The completion of the construction works.

0%

Registration Phase

Statement of Compliance

Statement of Compliance


The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

0%

Lodge Plan of Subdivision

Lodge Plan of Subdivision


The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

0%

Titles

Titles


The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor's reports.

0%

Show Details
Stage 8

The Jasmine Release

Civil
20
Registration

Estimated Title Registration

Q1 2023

Civil Phase

20%

Site Establishment

Site Establishment


This entails the contractor taking control of the total works area as detailed on the construction drawings. It also involves the delivery of site sheds, and pre-commencement approval from Council.

100%

Bulk Earthworks

Bulk Earthworks


The process of stripping off topsoil for reuse, removal and the reshaping of the ground to allow construction of roads and surface drainage to each lot. In addition, also includes placement of any fill material if required.

100%

Drainage Works

Drainage Works


The provision of underground drainage and channel/retarding basin drainage system of pipes and open channels for drainage of roads, public areas and the provision of a drainage point for each individual lot.

0%

Sewer Works

Sewer Works


The provision of trunk sewers and reticulation of sewer pipelines. These works also include the provision of a sewer connection point to each lot.

0%

Water & Gas Reticulation

Water & Gas Reticulation


The provision of water and gas pipelines with a connection to each lot.

0%

Subgrade Placement Works

Subgrade Placement Works


The engineered material that provides a firm base underneath a constructed road pavement.

0%

Electrical & NBN

Electrical & NBN


The supply of electricity and NBN (high speed internet) to each lot.

0%

Footpaths / Asphalt / Linemarking

Footpaths / Asphalt / Linemarking


The Footpaths are constructed along most of the road reserves in a residential subdivision. Kerb and Channel borders the road surface and provides drainage for storm water. Asphalt is a mixture of bituminous pitch with sand and gravel to provide a robust waterproof sealed surface for the road pavement.

0%

Practical Completion

Practical Completion


The completion of the construction works.

0%

Registration Phase

Statement of Compliance

Statement of Compliance


The formal confirmation from the Council stating construction works have been completed in accordance with approved plans to the satisfaction of all authorities.

0%

Lodge Plan of Subdivision

Lodge Plan of Subdivision


The Plan of Subdivision has been registered at Land Titles Victoria, which creates the individual titles for all lots included on the Plan allowing Settlement to take place.

0%

Titles

Titles


The provision of individual lot titles created by the Victorian land titles office, as per the Plan of Subdivision and the surveyor's reports.

0%

Show Details
Stage 25

The Maple Release

Civil
Registration

Estimated Title Registration

Q4 2023

Stage 26

The Yareena Release

Civil
Registration

Estimated Title Registration

Q4 2023

Stage 24

The Lily Release

Civil
Registration

Estimated Title Registration

Q4 2023

Stages Completed:

Stage 7

Stage 7

Stage 6

Stage 6

Stage 5

The Cedar Release

Stage 4

The Myrtle Release

Show More

Disclaimer: Estimated title dates are provided as an approximate guide only and are subject to change. The title date estimates provided are based on current information regarding the design, construction, and relevant authority approvals timeframes for the individual stage. Balcon uses this information to provide an estimate of the month (or month/quarter ranges) in which titles will be achieved however this is subject to change and may be influenced by factors which are outside Balcon’s control such as weather, contractor delays and authority inspections. Balcon is not bound by any of the information or date estimates set out on this webpage. Balcon does not give any warranty in relation to any information contained in this webpage and does not accept any liability for loss or damage arising as a result of any reliance on the information on this webpage. The sale of a lot at Orana by Balcon is subject to the conditions of a contract of sale entered into between the purchaser and the vendor of the lot. The contract of sale is the entire agreement between the vendor and purchaser. All purchasers should rely solely on the terms of the contract of sale and obtain their own independent legal advice in relation to the terms of the contract of sale.